| Purpose
|
| I. Handover of Pavilions etc
|
| II. Facility Construction
|
| |
1. Construction period etc
|
| |
2. Temporary office for construction
|
| |
3. Temporary supply of electricity and water for construction
|
| |
4. Temporary materials storage site
|
| |
5. Use of West Terminal
|
| |
6. Waste disposal
|
| |
7. Entry/exit of, and parking area for, construction workers
|
| |
8. Carry-in-and-out plans
|
| III. Emergency Measures
|
| |
1. Insurance
|
| |
2. Accident and sickness
|
| |
3. Security and fire prevention
|
| IV. Points of Note
|
| |
1. Legal compliance
|
| |
2. Construction management
|
| |
3. Considerations for safety and sanitation
|
| |
4. Participation in construction contractors’ meeting (coordination council)
|
| V. Miscellaneous Matters
|
| |
1. Traffic within Exhibition Site
|
| |
2. Meals
|
| |
Attachments
|
| |
1. Attachment 1: Notice of Appointment of Work Site Manager
|
| |
2. Attachment 2: Report on Commencement of Construction
|
| |
3. Attachment 3: Report on Completion of Construction |