Purpose
|
I. Handover of Pavilions etc
|
II. Facility Construction
|
|
1. Construction period etc
|
|
2. Temporary office for construction
|
|
3. Temporary supply of electricity and water for construction
|
|
4. Temporary materials storage site
|
|
5. Use of West Terminal
|
|
6. Waste disposal
|
|
7. Entry/exit of, and parking area for, construction workers
|
|
8. Carry-in-and-out plans
|
III. Emergency Measures
|
|
1. Insurance
|
|
2. Accident and sickness
|
|
3. Security and fire prevention
|
IV. Points of Note
|
|
1. Legal compliance
|
|
2. Construction management
|
|
3. Considerations for safety and sanitation
|
|
4. Participation in construction contractors’ meeting (coordination council)
|
V. Miscellaneous Matters
|
|
1. Traffic within Exhibition Site
|
|
2. Meals
|
|
Attachments
|
|
1. Attachment 1: Notice of Appointment of Work Site Manager
|
|
2. Attachment 2: Report on Commencement of Construction
|
|
3. Attachment 3: Report on Completion of Construction |